An-Najah University Journal for Research - A (Natural Sciences)

Scopus

Scopus profile and journal metrics

This journal is indexed in Scopus. Use these metrics for a quick publishing snapshot, then open the Scopus page for the authoritative profile.

Scopus
An-Najah University Journal for Research - A (Natural Sciences) Indexed in Scopus since 2019
CiteScore 0.8
Indexed since 2019
First decision 5 Days
Submission to acceptance 160 Days
Acceptance to publication 20 Days
Acceptance rate 14%

SCImago

SCImago Journal Rank preview

Use SCImago when you want a quick visual view of the journal ranking profile and external discoverability signals.

An-Najah University Journal for Research - A (Natural Sciences) SCImago Journal & Country Rank

DOAJ

Directory of Open Access Journals listing

The DOAJ record is useful for readers, librarians, and authors who want a direct open-access directory entry for the journal.

DOAJ
An-Najah University Journal for Research - A (Natural Sciences) Open directory record
original_full_paper

Quantity-Significant Models and their Use for Predicting Evaluation Curves

Published
2000-05-14
Pages
23 - 35

Abstract

Analysis of 14 reinforced bridge bills of quantities has shown that an integrated cost and time model containing at most 20 elements at the detailed design stage can predict total project value within accuracy ± 3%. Using the same number of elements the model can predict the project duration within accuracy: ± 5%. Quantity-significant work packages (qswp) were derived using trade- by- trade analysis, and a single cost model factor (cmf), and time model factor (tmf) were determined. Since the same elements used in the cost model are also used in the time model, a new approach to developing operational bills of quantities is highlighted. The new operational bill makes deriving and using the evaluation curve of a project much easier

Article history

Received
1999-03-15
Accepted
2000-05-14
Available online
2000-05-14
original_full_paper

نماذج الكميات المهمة واستخدامها للتنبؤ عن منحنيات التقييم

Published
2000-05-14
الصفحات
23 - 35

الملخص

من خلال تحليل اربعة عشر جدولا للكميات والأسعار في الجسور المسلحة، تمت ملاحظة أن التكلفة المتكاملة، ونمذجة الوقت، المحتوية لعشرين بندا على الأكثر في مرحلة التثميم الدقيق يمكن أن تستخدم في توقع قيمة المشروع الكلية وبدقة مقدارها ± 3%، وباستخدام نفس العدد من البنود المذكورة سابقاً، يمكن استخدام النموذج لتوقع فترة المشروع وبدقة ± 5%. الحزم التي تحتوي على البنود ذات الكميات الأكبر قد اشتقت لكل نوع عمل ومعامل نموذج الزمن ومعامل الكلفة قد حسب لكل واحدة منها على حدة.

Article history

تاريخ التسليم
1999-03-15
تاريخ القبول
2000-05-14
Available online
2000-05-14