Quantity-Significant Models and their Use for Predicting Evaluation Curves


Article info

1999-03-15
2000-05-14
2000-05-14
23 - 35

Keywords

Abstract

Analysis of 14 reinforced bridge bills of quantities has shown that an integrated cost and time model containing at most 20 elements at the detailed design stage can predict total project value within accuracy ± 3%. Using the same number of elements the model can predict the project duration within accuracy: ± 5%. Quantity-significant work packages (qswp) were derived using trade- by- trade analysis, and a single cost model factor (cmf), and time model factor (tmf) were determined. Since the same elements used in the cost model are also used in the time model, a new approach to developing operational bills of quantities is highlighted. The new operational bill makes deriving and using the evaluation curve of a project much easier

نماذج الكميات المهمة واستخدامها للتنبؤ عن منحنيات التقييم


معلومات المقال

1999-03-15
2000-05-14
2000-05-14
23 - 35

الكلمات الإفتتاحية

الملخص

من خلال تحليل اربعة عشر جدولا للكميات والأسعار في الجسور المسلحة، تمت ملاحظة أن التكلفة المتكاملة، ونمذجة الوقت، المحتوية لعشرين بندا على الأكثر في مرحلة التثميم الدقيق يمكن أن تستخدم في توقع قيمة المشروع الكلية وبدقة مقدارها ± 3%، وباستخدام نفس العدد من البنود المذكورة سابقاً، يمكن استخدام النموذج لتوقع فترة المشروع وبدقة ± 5%. الحزم التي تحتوي على البنود ذات الكميات الأكبر قد اشتقت لكل نوع عمل ومعامل نموذج الزمن ومعامل الكلفة قد حسب لكل واحدة منها على حدة.

These articles may interest you also

An-Najah National University
Nablus, Palestine
P.O. Box
7, 707
Fax
(970)(9)2345982
Tel.
(970)(9)2345560
(970)(9)2345113/5/6/7-Ext. 2378
E-mail
[email protected]
Dean
Prof. Waleed Sweileh